5 FAH-11 H-411 INTRODUCTION
5 FAH-11 H-411.1 Purpose
(CT:IAH-9; 04-06-2017)
a. This subchapter establishes procedures to implement
system authorization of non-Department entity systems that process information
on behalf of the Department as set forth in is 5 FAM
1066.1-1(F). These systems either connect to Department information
systems, or process/store Department information without establishing a
connection.
NOTE: Non-Department
entity refers to U.S. Government civilian and military personnel, consultants,
contractors, foreign, state, local governments or organizations, and other
individuals that require access to Department information systems. This
includes entities that provide information technology (IT) services and related
computer industry support that contribute to the efficient functioning of the
Department.
b. This subchapter will assist sponsoring bureaus to
implement processes that protect Department information and information systems
from operational, strategic, and legal risks that a non-Departmental system may
present.
c. The Non-Department System Authorization Process is
designed to certify that a non-Departmental system meets documented security
requirements, and will continue to maintain the accredited security posture
throughout the authorized system's life cycle.
5 FAH-11 H-411.2 Objective
(CT:IAH-5; 06-25-2007)
a. The Federal Information Security Management Act of
2002 (FISMA) requires that all systems that process or store Department
information must be certified and accredited.
b. Implementation of this subchapter will help to
enable secure information exchange, collaboration, and interoperability among
Department bureaus and other federal, state, and local agencies.
c. The Office of Information Assurance (IRM/IA) is the
responsible office for the contents of this chapter. Send questions or
comments to the IRM/IA e‑mail address, informationassurance@state.gov.
5 FAH-11 H-411.3 Scope
(CT: IAH-9; 04-06-2017)
a. This subchapter outlines the procedures that must be
met to achieve non-Department system authorization. Types of connectivity to
Department information systems are identified in 5 FAH-11 H-800,
Connections to Non-Department Entities.
b. Bureaus that sponsor non-Department system
authorization must use the process established in this subchapter to meet the
Authorizing Official's (AO) (formerly known as the Designated Approval
Authority (DAA)) authorization requirements whether or not connectivity is
achieved.
c. These procedures exclude authorization of Sensitive
Compartmented Information (SCI) systems. Systems that process or store
national security level information are processed for authorization in
accordance with applicable Federal and Department requirements for
authorization of classified and SCI systems (see 12 FAM 630, 12
FAH-6, and NISPOM-Chapter 8, DD-254, and DOSAR). The Bureau of Diplomatic
Security (DS) is the Security Assessor, and the Bureau of Intelligence and
Research (INR) is the AO for SCI systems at the Department (see 1 FAM 271.1,
subparagraph (4).)
d. This subchapter does not apply to non-Department
systems used with the Department's telework solution. (See 12 FAM 091 for
definition of automated information system.)
5 FAH-11 H-411.4 Oversight Of
Non-Department System
(CT:IAH-9; 04-06-2017)
a. The Department, as required by FISMA, must ensure
that non-Department entities develop, implement, and maintain a baseline of
minimum security controls to protect Department information and information
systems. The policy requirements for non-Department systems are set forth in 5 FAM
1066.1-1(F).
b. In 2005, the Department developed, documented in its
Information Security Program Plan (ISPP) (under Management Plan), and
implemented an ongoing Department-wide information security program to protect
its information and information systems. This program details the oversight
management which extends to those non-Department systems delivering IT systems
and services to or on behalf of the Department.
5 FAH-11 H-411.5 Key Personnel
(CT:IAH-9; 04-06-2017)
a. Key personnel, identified to perform certification
and accreditation (C&A) of a non-Department system, must not be involved
with its development, implementation, or operation (see 5 FAM
1066.1-1(D)), or be under the sponsoring bureau's direct management
authority.
b. Members of the authorization team must consist of a
combination of key staff members assigned to participate in C&A of a system
when operating under Department authority. Authorization team members must
have the appropriate level of experience and credentials for the positions
assigned. They must also be able to fulfill the responsibilities of the
following roles:
(1) Sponsoring bureau representative;
(2) System manager and/or vendor representative;
(3) Certification team lead (must be independent for
moderate or high impact systems);
(4) Certification analyst(s) for operating system and
database;
(5) Risk management team lead;
(6) Risk analyst;
(7) User representative (where needed); and
(8) Other key participants having an interest in the
C&A outcome.
c. Non-Department entities must furnish their results
for any non-Department system independent C&A to the sponsoring bureau representative
and to IRM/IA for compliance evaluation with the requirements of this
subchapter.
d. Key staff members working to certify and accredit a
system must:
(1) Coordinate user participation, when necessary;
(2) Participate in reviews and interviews; and
(3) Provide review and input for the teams
deliverables.
e. Authorization team members may perform multiple
roles or several members may work together to fulfill one role since duties may
vary based on the nature of the accreditation task.
5 FAH-11 H-412 ROLES AND
RESPONSIBILITIES FOR NON-DEPARTMENT SYSTEMS AUTHORIZATION
5 FAH-11 H-412.1 Authorizing
Official (AO)
(CT:IAH-11; 08-10-2017)
a. The Chief Information Officer (CIO) is the authorizing
official (AO) for systems at the Department that are designated unclassified up
through collateral Top Secret (TS). The AO's approval requirements must be
stated in the formal agreement established by contractual arrangement between
the sponsoring bureau and the non-Department entity. The CIO makes the
decision to authorize or deny authorization of a non-Department system. (See 1 FAM 271.1,
subparagraph (4).)
b. The Bureau of Diplomatic Security (DS) is the security
assessor and the Bureau of Intelligence and Research (INR) is the AO for State
systems that fall under the requirements of the Intelligence Community
Directive 503 for Protecting Sensitive Compartmented Information (SCI) within
information systems.
c. The CIO also works with program officials, budget
officers, inspectors general, and other appropriate agency officials, to
develop a Plan of Actions and Milestones (POA&M) report to the Office of
Management and Budget (OMB) for each non-Department system for which a weakness
is identified during annual FISMA reports. The IRM/IA Web site contains
requirements and instructions for completing the POA&M.
5 FAH-11 H-412.2 Chief Information
Security Officer (CISO)
(CT:IAH-8; 12-22-2016)
a. The Chief Information Security Officer (CISO) heads
IRM/IA and oversees and manages compliance with the requirements imposed on the
sponsoring bureau during authorization of a non-Department system under the
CIOs direction. (See 44 U.S.C. 3554.)
b. The CISO defines and oversees the process and
requirements for meeting a non-Department system authorization.
NOTE: The independent
certification authority performing certification of a system must show that the
level of information security is appropriate to protect the integrity,
confidentiality, and availability of Department information and information
systems.
5 FAH-11 H-412.3 IRM/IA
(CT:IAH-11; 08-10-2017)
IRM/IA evaluates a percentage of the completed system
authorization packages annually to ensure compliance with Department assessment
and authorization (A&A) processes and standards.
NOTE: Requirements for independent
authorization are in 5 FAM 1066.
5 FAH-11 H-412.4 Sponsoring Bureau
(CT:IAH-15; 11-07-2018)
a. The bureau sponsoring authorization of a system is
responsible for the secure operation of Department information systems accessed
by a non-Department system. The sponsoring bureau must ensure that controls
are in place to protect Department information that is processed or stored at a
non-Department entity's facility.
b. The sponsoring bureau must ensure that the
supporting documentation required for AO authorization of a non-Department
system is generated.
NOTE: Refer to the
documentation requirements in 5 FAH-11 H-820
for establishing and governing connections with non-Department entities in
instances where connectivity is an issue.
c. The sponsoring bureau must send a memo to the CISO
explaining the basic functions and purpose of the system and indicating that
the system is entering into the non-Department system authorization process.
Once a system is entered into the non-Department system authorization process,
the sponsoring bureau must:
(1) Exercise program control over Department
information systems under their management authority that will exchange
information with a non-Department entity that is allowed access to process or
store information on behalf of the Department;
(2) Represent the non-Department systems interest to
the Department throughout its lifecycle;
(3) Ensure that the non-Department entity establishes
and documents the unclassified and classified baseline security control
configuration for the information system seeking AO authorization (see
Department of State Security Control Baseline Process and Security Control Catalog
For Unclassified Systems, and 12 FAM 630).
The identified security controls must be documented in the systems System
Security Plan (SSP) and Contingency Plan (CP) as generated by the
non-Department entity;
(4) Register the system in the Information Management,
Analytics, and Technology Resource for Information Exchange (iMATRIX), and
ensure the systems security categorization process is completed in accordance with Department requirements.
(See the iMATRIX website for more information on registering IT assets in
iMatrix);
(5) Ensure that the non-Department entity completes
the security categorization for unclassified systems in accordance with the
latest FIPS Publication 199 requirements;
(6) Determine the sensitivity level of Department
information processed or stored in the system, and define the functions users
are permitted to perform when accessing the system;
(7) Ensure that the non-Department entity implements
system baseline security controls that meet federal mandates to protect information
commensurate with its sensitivity level and classification and assure the
controls are in compliance with Department policy and guidelines for security
control selection:
(a) Unclassified Systems: The categorization of
information must determine the impact level (see FIPS Publication 199 and NIST
Special Publication (SP) 800-60) of the processing system, and, as categorized,
minimum baseline controls must be implemented in accordance with the Security
Control Baseline Process and Security Control Catalog for Unclassified Systems;
and
(b) Classified Systems: The classification of the
information (Confidential, Secret, Top Secret), combined with availability and
integrity impact, must
(i) Determine the baseline controls from the
National Industrial Security Program Operating Manual (NISPOM) Chapter 8,
DD-254, Department of State Acquisition Regulations (DOSAR), and Department
specific controls identified for systems processing or storing classified
information on behalf of the Department; and
(ii) Supplement the security control baseline in
accordance with Department policy (see 12 FAM 630 and
12 FAH-6);
(8) Identify key stakeholders that will participate as
members of the independent accreditation team. This includes identifying the
user representative for the system, and sponsoring bureau participants
appointed as facilitators to handle key functions that support A&A of the system;
(9) Identify, assess, prioritize, and monitor the
progress of corrective efforts (remediation) of security weaknesses
(vulnerabilities) found in the system under the sponsoring bureaus management
authority; and
(10) Work with the CIO to report to OMB the status of
implementation of planned security controls and/or remediation of identified
deficiencies of the system security controls listed in the systems POA&M
report. The quarterly submissions of POA&M reports to OMB should include,
but not necessarily replace, all Department security remediation plans. (See
OMB memorandum M-17-26 for guidance on
reporting the results of security reviews and evaluations.)
d. Systems currently processing or storing information
on behalf of the Department without authorization from the AO must be
immediately reported to DS/SI/CS and IRM/IA. Also report systems connected to
the Departments networks to IRM/OPS. All non-Department systems must be
entered into the non-Department system authorization process by the sponsoring
bureau. The sponsoring bureau must notify DS, IRM/OPS and IRM/IA with the
required system information. The CIO may deny authorization of the system if
the sponsoring bureau fails to enter the unauthorized system into the non-Department
system authorization process.
e. The sponsoring bureau must coordinate and monitor
the activities of information security practitioners assigned to independently
certify and accredit a non-Department system.
NOTE: Independent
certification is required for moderate or high impact level unclassified and
all classified systems. Low impact systems do not require independent certification.
5 FAH-11 H-412.5 Assessment Team
(CT:IAH-11; 08-10-2017)
a. The assessment team must ensure all required
controls specified in the SSP of a non-Department system that processes or
stores Department information have been appropriately scoped and are addressed.
b. The assessment team must evaluate all controls
specified in the non-Department system SSP to the level of rigor required for
the systems designated impact level.
c. Only the lead assessor must meet the requirements
for independence as specified in 5 FAM 1066 in
circumstances where independent certification is required.
d. All assessment analysts must perform assessment in
accordance with 5
FAH-11 H-200, Certification (Information Security Audit).
5 FAH-11 H-412.6 Authorization Team
(CT:IAH-11; 08-10-2017)
a. The authorization team is responsible for scoping
the initial security control baseline by using an assessment of risk and
potential harm to the Departments mission from a non-Department system and
documenting the resulting baseline in the SSP.
b. The authorization team analyst assigned to assess
risk for a system undergoing accreditation under the non-department system authorization
process must perform the following activities:
(1) Assess and document the risk and potential impact
posed from this system which accesses Department information and information
systems;
(2) Evaluate, determine the scope, and identify the
minimum security controls to meet the requirements in this subchapter for
unclassified systems. The analyst must use the results of the documented risk
and potential impact posed from this system. (See the latest security control Baseline
process and Security Control Catalog for Unclassified Systems process guide,
available on the IRM/IA Web site);
(3) Ensure that all requirements mandated in 12 FAM
600 and 12 FAH-6, have been incorporated into the SSP for classified non-SCI
systems; and
(4) Recommend the level of managed risk to the AO for
authorization approval or denial upon completion of the system certification.
(a) Systems with overall high residual risk require the
authorization team analyst to make a recommendation to the AO to deny
authorization. Systems with overall medium residual risk require the
authorization teams analyst to make a risk-managed authorization
recommendation to the AO based upon information supplied by the sponsoring
bureau. This may include, but is not limited to, business need, scoping
justifications, compensating security controls, and reasonable completion dates
for remediation of medium risk items. The recommendation to the AO may be to:
(i) Grant the system a full authorization for 36
months;
(ii) Grant a full authorization for less than 36
months;
(iii) Grant a full authorization with stipulations
pertaining to remediation of medium risk items; or
(iv) Deny authorization; and
(b) Systems with low risk require the authorization team
analyst to make a recommendation that the AO approve authorization.
c. Besides a recommendation to the AO to approve or
deny a non-Department system authorization, the Authorization Memorandum
generated by the authorization team analyst must include:
(1) A brief description of the system operating
environment and accreditation boundary, including hardware/software
configurations, and the applications that fall within the accreditation
boundary;
(2) A detailed presentation of the assessed risk
affecting the authorization decision; and
(3) The systems initial POA&M report.
NOTE: This report must
translate the results of the Security Assessment Report into the standard
POA&M format, and should be used to facilitate communication back to the
sponsoring bureau concerning the vulnerabilities found in connecting to a
system.) (See the IRM/IA Web site for more information on preparation and use
of the Authorization Memorandum.
5 FAH-11 H-413 PROCEDURES FOR SYSTEM
AUTHORIZATION OF NON-DEPARTMENT SYSTEMS
5 FAH-11 H-413.1 General
(CT:IAH-5; 06-25-2007)
a. Non-Department entities must undergo system
authorization under the non-Department system authorization process if:
(1) The sponsoring bureau demonstrates a business need
that the non-Department entity fills; or
(2) Department information is being, or is planned to
be processed or stored on a non-Department system; or
(3) Department required legal contractual arrangements
are in place between the sponsoring bureau and the non-Department entity.
b. The sponsoring bureau facilitates certification and
accreditation (C&A) of a non-Department system. The four aspects that
encompass C&A are:
(1) Technical review and evaluation: Verify through
independent technical review and evaluation the existence of the minimum
required security controls in and around the system for low, moderate, and high
impact unclassified and all classified systems;
(2) Testing: Test the effectiveness of the
implemented or planned baseline security controls. These controls must provide
sufficient protection, commensurate with the level of information that the
controls protect;
(3) Risk-managed processes: Involve senior management
in the security lifecycle, and provide sound operational decisions, based on an
identified, objective, risk-managed process; and
(4) Authorization: Achieve full authorization to
operate for the maximum time allowable, up to three years, using a
risk-management process. Authorization requires that:
(a) Mission effectiveness is balanced with security
requirements and risk management;
(b) Appropriate officials are assigned to manage
responsibilities commensurate with their designated roles and security
responsibilities; and
(c) Authorization of systems that process or store
Department information is achieved either prior to operations, or as currently
operational.
5 FAH-11 H-413.2 Certification
Requirements
(CT:IAH-11; 08-10-2017)
a. All moderate and high impact unclassified, and all
classified systems seeking authorization must have independent certification
(see 5 FAM
1066.1-1(D)).
b. Low impact unclassified systems do not require
independent certification but may be certified using resources provided by the
sponsoring bureau.
c. Systems undergoing certification that are connected
to the Department must be in compliance with the requirements in 5 FAH-11
H-822.5.
d. The certification package must meet the Departments
C&A requirements for system authorization. The sponsoring bureau must
verify that:
(1) The security controls, put in place to protect the
Department's unclassified information and information systems, are in
compliance with the requirements in the FIPS Publication 200, the most current
version of NIST SP 800-53, 12 FAM 600, 5 FAM, and 12 FAH-6;
(2) The security controls, put in place to protect the
Departments classified information and information systems, are in accordance
with the requirements in 12 FAM 600 and 12 FAH-6; and
(3) See the DS/SI/CS and IRM/IA online security resources
library for the most current classified and unclassified security control
catalogs. The catalogs map Department and additional national level
requirements that must be met in order to comply with the NIST SP 800-53
security controls.
5 FAH-11 H-413.3 Authorization
Requirements
(CT:IAH-5; 06-25-2007)
All non-Department systems processing or storing
Department information, whether via a connection or not, are required to enter
and complete the non-Department system authorization process before DAA
authorization is granted:
(1) New systems must complete the non-Department system
authorization process and receive DAA authorization before being allowed to
process or store Department information; and
(2) Systems identified as operating without DAA
authorization may be required to cease operations. However, at the discretion
of the CIO, and only to meet a critical business need, these systems may be
allowed to continue operations, provided the sponsoring bureau makes arrangements
with the non-Department entity to begin system authorization of the identified
system. Upon identification, authorization must be achieved within three
months, or the system may be disconnected.
5 FAH-11 H-413.4 Non-Department
System Authorization Process Phases
(CT:IAH-5; 06-25-2007)
Authorization of unclassified non-Department systems
progresses through four phases and is similar to the Departments system authorization
process. The phases include initiation, certification, accreditation, and life
cycle monitoring. Individuals conducting C&A of a non-Department system
must be familiar with all four phases of this process.
5 FAH-11 H-413.4-1 Phase I
Initiation Phase
(CT:IAH-5; 06-25-2007)
The sponsoring bureau must, at a minimum, complete and
provide the documentation listed in 5 FAH-11
Exhibit H-413.4-1.
5 FAH-11 H-413.4-2 Phase II
Certification Phase
(CT:IAH-5; 06-25-2007)
Certification must validate compliance of a system with
the minimum mandatory security controls that are defined within the
non-Department systems SSP. (See IRM/IAs Web site for the latest minimum
mandatory security controls.) The certification requirements (Phase II) are
listed in 5
FAH-11 Exhibit H-413.4-2.
5 FAH-11 H-413.4-3 Phase III
Accreditation Phase
(CT:IAH-5; 06-25-2007)
Accreditation produces the required evidence to support
the Designated Approval Authority (DAA) in making an informed, risk-managed
decision to approve or deny authorization of a non-Department system. The risk
analyst generates an authorization package created during the certification phase.
Accreditation requirements are in 5 FAH-11
Exhibit H-413.4-3.
5 FAH-11 H-413.4-4 Phase IV Life
Cycle Monitoring Phase
(CT:IAH-5; 06-25-2007)
The sponsoring bureau is responsible for audit and
continuous monitoring of non-Department systems that it sponsors for
authorization. Audits must validate that these systems do not compromise the
integrity, availability or confidentiality of Department information systems,
or the information processed or stored on behalf of the Department. Life cycle
monitoring (Phase IV) requirements are in 5 FAH-11
Exhibit H-413.4-4.
5 FAH-11 H-414 Procedure For a Targeted
Security Control Assessment
(CT:IAH-5; 06-25-2007)
a. A targeted security control assessment (SCA) is
performed by the certification analyst to validate whether or not remediated
items are successfully mitigated.
b. A risk analyst reviews the targeted SCA results to
determine the level of residual risk:
(1) The system may be recommended for full authorization
if, after remediation, residual risk is determined to be low; and
(2) The system may not be recommended for full
authorization until such time that risk is remediated to an acceptable level
(low), if remediation is not completed, or remediation did not mitigate
unacceptable risk to low.
c. The DAA can authorize a system with medium and high
residual risk. The sponsoring bureau must first make every effort to reduce
the risk to low. Next, the sponsoring bureau must send a memorandum to DAA that
outlines a supporting business case which demonstrates a critical business need
that overrides the security concerns.
d. Updates to documents that may have been affected by
re-entry into an earlier phase of the non-Department system authorization process
must be reviewed by the sponsoring bureau to ensure that any changes in the
system's baseline, necessary to support re-entry into the process, are
accurately recorded.
5 FAH-11 H-415 REACCREDITATION OF
NON-DEPARTMENT SYSTEMS
5 FAH-11 H-415.1 General
(CT:IAH-11; 08-10-2017)
a. Reaccreditation of systems can be event-driven (e.g.
upgrades, laws, regulations, directives, instructions or policies that dictate
such activity change), or time-driven (e.g., the authorization has expired).
Examples include:
(1) Event-driven can be represented through a
significant system change that requires reaccreditation or the systems
operating environment changes to the degree that threats formerly rated as low
are now significant enough for reaccreditation;
NOTE: A significant
change is one that alters the authorized configuration to the degree that
reaccreditation must be considered. Adding a new function or application that
establishes a new interconnection with other agencies or non-Department
entities is an example;
(2) Time-driven supports OMB Circular A-130
requirements to re-accredit a system every three years; and
(3) Changes to laws that define the requirements for
protecting a systems baseline controls can be either event- or time-driven.
(For example, FISMA and other laws and regulations control processing
requirements of unclassified and classified national security information and
direct that a systems minimum security controls be sufficient to protect the
agencys information and information systems commensurate with the sensitivity
level and classification of the information processed. The authorization of a
system could be affected and must be evaluated for reaccreditation if these
laws and regulations change and the changes are significant.)
b. Authorized systems must be reaccredited prior to
expiration of their current authorization:
NOTE: The sponsoring
bureau should process the system for reaccreditation within three months prior
to the expiration date of the systems current authorization to allow time for
recertification to occur.
(1) The sponsoring bureau must validate that the
system meets policy, guidelines, and procedures which require and recommend
adequate security controls that balance risk and business needs in submitting a
non-Department system for reauthorization; and
(2) Reauthorization of this system is dependent upon
the outcome of DAAs review of Accreditation Recommendation to approve or deny
authorization and the residual risk posed to Department information systems.
c. The DAA authority may take the following actions if
reaccreditation cannot be completed before expiration of the systems current
authorization:
(1) Approve an authorization extension until
reaccreditation is achieved and the system is authorized to operate;
(2) Direct that operations cease, and the system be
disconnected and removed from the Departments iMATRIX (integrated management, analytics,
and technology resource for information exchange); or
(3) Accept the risk and authorize the system. In this
case, every effort to reduce risk to low must be exhausted, and the sponsoring
bureau must demonstrate that a critical business need overrides the security
concerns.
d. Sponsoring bureaus must ensure that their sponsored
non-Department unclassified system is compliant with the latest FIPS 200
requirements when submitting a system for reaccreditation. Security control
sets must be validated and selected under the Department's latest implemented
Security Control Baseline Process and Security Control Catalog for Unclassified
Systems. (See 5 FAH-11
H-412.6 paragraph b(3) above for security controls for classified systems.)
e. System reaccreditation begins at the initiation phase
(phase I), and progresses through all tasks initially completed during the
original accreditation, and ends at the lifecycle monitoring phase (phase IV).
f. All phases of the non-Department system authorization
process must be successfully completed before a system is once again granted
full authorization to process or store Department information.
5 FAH-11 H-415.2 Reaccreditation Of
Non-Department Systems Resulting From A Significant Change
(CT:IAH-5; 06-25-2007)
a. Reaccreditation of a system is required whenever a
significant change is made to the accredited system's baseline. Proposed
modifications to a system (including software, firmware, hardware, or
interfaces and interconnections to networks) must be jointly reviewed by the
sponsoring bureau and IRM/IA to determine if the proposed modifications will
impact the connecting systems (and subsequently the Department systems)
protection profile.
b. The DAA may extend authorization to continue to
process or store information until reaccreditation is completed and full
authorization is once again granted in cases where a non-Department systems
authorization has expired, or is about to expire but has been submitted for or
is undergoing reaccreditation.
c. The sponsoring bureau must assess the risk in cases
where a system is undergoing major modifications. The risk must be lower than
moderate to high risk before the system can qualify for an authorization
extension.
d. The sponsoring bureau must submit a memo to the DAA
indicating that reaccreditation for the specified system is due at least three
months prior to expiration of the systems current authorization, unless
circumstances dictate otherwise. A non-Department system must be scheduled for
reauthorization upon submittal of the reaccreditation request memo.
5 FAH-11 H-415.3 Reaccreditation Of
Non-Department Systems Without Significant Change To Baseline Configuration
(CT:IAH-5; 06-25-2007)
a. The sponsoring bureau must ensure that the system
complies with all applicable Department Security Configuration Guidelines if an
authorized system is due for reaccreditation and has not undergone any
significant change to its baseline configuration.
b. The sponsoring bureau should conduct a spot check of
the system to ensure the original documentation and evidence, used in the
former authorization, still applies. If so, the sponsoring bureau will
coordinate their efforts. Accomplish this by:
(1) Department-approved application scans of the
system;
(2) Documentation review (specifically the SSP and
CP); and
(3) Review of waivers and/or exceptions applied for
and granted since authorization of the system.
c. The sponsoring bureau must review the results of
Department-approved scans and system documentation provided by the
non-Department system owner for configuration compliance, including the summary
status of POA&Ms from the previous assessment. In the event no new
vulnerabilities are noted:
(1) The current authorization must be amended to
reflect no significant changes have occurred, and no new vulnerabilities were
found that require remediation action;
(2) The systems current authorization date must
remain unchanged; and
(3) The sponsoring bureau must recommend that the DAA
approve reauthorization of the system extending up to three years from
expiration date of its current authorization.
d. If conducting a spot check and it is determined that
new vulnerabilities exist because of a significant change in the systems
baseline configuration, the non-Department system may be required to undergo
re-certification and reaccreditation in phases I through III before granting
reauthorization.
e. The DAA may require the system to undergo a targeted
C&A in accordance with the requirements in this subchapter if authorization
of a moderate or high application is due to expire.
5 FAH-11 H-415.4 Requirements for
Addressing Baseline Configuration Changes To Non-Department Systems
(CT:IAH-11; 08-10-2017)
a. The sponsored non-Department entity must notify the
sponsoring bureau prior to implementation of the change if an authorized system
is due to undergo a significant change to its baseline configuration.
b. The sponsoring bureau must ensure that system
updates are complete if a system is not authorized but is scheduled for C&A
under system authorization. On the other hand, this bureau can instead request
that the system remain unchanged in its current baseline configuration before
system authorization is allowed to start or continue.
c. Requested changes to a non-Department systems
baseline configuration must be assessed for their impact on the Departments
infrastructure (systems operations, and/or security.)
(1) The non-Department entity must provide the
sponsoring bureau a Business Impact Summary, clearly stating the business
impact the proposed changes may have to the system. (See IRM/IAs Web site for
instructions on preparing this summary.); and
(2) The assigned independent certification analyst
must review the request to confirm whether or not the change is significant
enough to warrant reauthorization:
(a) A memo from the sponsoring bureau to the
non-Department entity must be issued stating reauthorization is not required if
the request is not a major change to the baseline;
(b) The reauthorization process must continue if the
request describes a major change to the baseline; and
(c) The independent certification and accreditation team
should confer or meet with the sponsoring bureau if further investigation is
required to determine if the change is major.
d. The sponsoring bureau must approve and manage
changes to a non-Department systems baseline configuration under strict
configuration management requirements. All changes must be promptly recorded
in the systems SSP and CP, where appropriate. Additional security controls
which affect a systems security posture must be implemented in accordance with
requirements in the Department's Security Control Baseline Process and Security
control Catalog for Unclassified Systems.
e. Unauthorized and/or undocumented changes to the
systems accredited baseline configuration may invalidate the systems
authorization.
f. The sponsoring bureau must ensure that changes to a
non-Department system are authorized, documented, and registered accordingly.
5 FAH-11 H-416 END OF LIFE CYCLE
REQUIREMENTS FOR NON-DEPARTMENT SYSTEMS
5 FAH-11 H-416.1 Criteria For
Disposal Of Non-Department Systems
(CT:IAH-8; 12-22-2016)
a. A system reaching the end of its lifecycle must be
disposed of in a secure manner (see 12 FAM 620).
b. The non-Department entity must generate and forward
the request for disposal of the unclassified system to the sponsoring bureau.
c. The assigned certification analyst and the
sponsoring bureau must review the disposal request and timeframe to:
(1) Ensure the system is properly scheduled for
disconnection from the Department information system;
(2) Determine the system is safe to shut down and that
safe disposal is coordinated in accordance with Department regulations (See 12 FAM 623.1);
(3) Inform iMATRIX of the request to retire a system
and remove it from the Departments integrated management, analytics, and technology
resource for information exchange; and
(4) File the request for disposal, and any other
documentation confirming the safe disposal, in IRM/IAs documentation library.
d. The IRM/OPS and the sponsoring bureau must jointly
investigate issues of improper system disconnection and disposal, and
scheduling of disposal, iMATRIX filings or disagreements with a disposal
request. IRM/OPS will inform all affected parties of the appropriate actions
in consideration for proper disposal of a system in the above instances and in
anticipation of a non-Department systems shutdown.
e. The areas the sponsoring bureau must address before
elimination of a system includes, but not limited to the:
(1) Archiving of information;
(2) Disposal of hardware, firmware, and software; and
(3) Sanitization of media.
f. The sponsoring bureau must accomplish, at a
minimum, the following management tasks when a system reaches the end of its
lifecycle:
(1) Send a memo to iMATRIX indicating system disposal;
(2) Contact iMATRIX maintenance to update the
application status to indicate that the system is submitted for retirement and
disposal (including systems disposal date); and
(3) Inform bureau staff and affected parties outside
the bureau that a retirement application is submitted and pending approval, and
that system disposal is imminent.
g. An extension to accommodate system disposal may be
granted for unclassified systems scheduled for retirement and disposal within
four months after the expiration date of their authorization. In this event,
the sponsoring bureau must:
(1) Send the CIO an extension request. The extension
request must include a business case that justifies an extension and the
conditions under which it is requested:
(a) If granted, the system will not need to undergo
re-accreditation, but instead will be retired and disposed of as scheduled;
(b) If denied, the system must be turned off and
disconnected upon expiration of its current authorization and before the actual
disposal date; and
(2) Have approved extensions in effect starting upon
expiration date of a systems authorization, and remain in effect until system
disposal is completed.
h. Classified systems must be disposed of in accordance
with Department guidelines and requirements.
5 FAH-11 H-417 THROUGH H-419 UNASSIGNED
5 FAH-11 Exhibit H-413.4-1
Phase I Initiation
(CT:IAH-8; 12-22-2016)
a. Start the initiation process.
(1) Memo request for system authorization activities.
(2) A Security Categorization Form, also referred to
as IT Asset Categorization form (for more information on how to complete the
Security Categorization Form and register a system, refer to the iMATRIX
website):
(a) If the system is already entered in iMATRIX, this
form will collect the remainder of the necessary information; and
(b) If the system is not registered in iMATRIX, the
sponsoring bureau must register it after completing this form.
(3) System Security Plan (SSP). All systems seeking
authorization under the non-Department system authorization process, whether
classified or unclassified, must have a SSP, that, as a minimum:
(a) Is current with the systems baseline configuration;
(b) Defines the systems baseline security controls; and
(c) Accurately reflects the systems accreditation
boundary.
(4) Contingency plan (CP). If required, the CP must
prescribe how the system is to be recovered to full operation in the event that
risk is realized and the system loses its integrity, confidentiality, or
availability. Not every system requires a CP. However, based on the system
type, systems must have a CP if they support critical Department operations:
(a) General support systems (GSS) and major applications
(MA) critical to operations and mission support of the Departments
infrastructure;
(b) Systems that process sensitive information,
including but not limited to, Health Insurance Portability and Accountability
Act of 1996 (HIPAA), Federal Managers Financial Integrity Act (FMFIA), and
Privacy Act information; and
(c) Systems supported by a single server, which in turn
support operations critical to the Department or bureaus mission.
b. Registration in iMATRIX. For more information on
how to register a systems integrated management, analytics, and technology resource
for information exchange in the iMATRIX, refer to the iMATRIX website.
c. The sponsoring bureau must define the system,
including its:
(1) Support role;
(2) Operating environment;
(3) Supporting applications (hardware/software
configuration); and
(4) Boundary of operation.
d. Once the above (phase I) requirements are completed,
the sponsoring bureau and the assigned IRM/IA personnel, with senior management
support from the non-Department entity, jointly develop a project work plan,
under the direction of IRM/IA, which formally establishes project milestones
and resources necessary to achieve authorization.
e. The forms and automated tools needed by the
sponsoring bureau to complete their components of the authorization process are
located on the IRM/IA Web site under "systems authorization."
f. IRM/IA personnel must verify that the sponsoring
bureau completed all documentation to required department standards before a
system can move from the initiation phase (phase I), to the certification phase
(phase II).
g. Items that may prevent completion of phase I
requirements include, but may not be limited to:
(1) Incomplete or insufficient documentation;
(2) Scheduling conflicting events that interfere with
the SCA;
(3) Lack of completion of phase I milestones planned
for certification and accreditation of the system; and
(4) Escalated and unresolved issues within the ongoing
certification and accreditation process.
h. Refer to the IRM/IA Web site for more information on
(1) asset registration requirements, (2) forms using available automated tools,
and (3) the latest Automated CP/SSP Tool Guide for generating system security,
and contingency plans.
5 FAH-11 Exhibit H-413.4-2
Phase II Certification
(CT:IAH-8; 12-22-2016)
a. IRM/IA or the sponsoring bureau must ensure that
certification of a non-Department system is accomplished in accordance with phase
II certification requirements, whether performed independently or not. This
includes requirements to:
(1) Prepare and perform the security control
assessment (SCA);
(2) Compile the SCA results (findings); and
(3) Generate the Certification Report and notify
IRM/IA of its completion at the end of the certification phase (phase II).
b. To ensure that the system is ready for a SCA, the
sponsoring bureau must validate that:
(1) Support requirements (time and resources) for its
completion will be met; and
(2) The system is not undergoing, or is not scheduled
to undergo, major changes to its baseline configuration that may interfere with
the SCA.
c. If independent certification of a system is
required, and the sponsoring bureau:
(1) Requests IRM/IA assistance, the certification
analyst, under authority and direction of the CISO, must:
(a) Perform a SCA;
(b) Compile SCA results (findings); and
(c) Generate the Certification Report and notification
to the IRM/IA advocate of its completion at the end of the certification phase
(phase II); or
(2) Does not request IRM/IA assistance, the sponsoring
bureau, under authority and direction of CISO, must ensure that:
(a) The SCA is performed in accordance with the
Departments non-Department system authorization process (found in this
subchapter);
(b) The non-Department entity provides the sponsoring
bureau the compiled SCA results (findings), which the sponsoring bureau
forwards to IRM/IA for review; and
(c) The non-Department entity generates and provides the
Certification Report upon completion of the SCA to the sponsoring bureau, who
in turn forwards it to IRM/IA upon completion of the certification phase (phase
II).
d. After verifying that the Certification Report is
completed in the proper format, it will be released to risk management for
assignment and analysis.
e. The risk analyst, assigned by IRM/IA risk management
to review the Certification Report, must:
(1) Analyze the SCA findings. If after analysis, the
risk analyst determines that issues in the Certification Report need resolving,
the process cannot move into the accreditation phase (phase III). All issues
with SCA findings must be resolved between the certification analyst and the
risk analyst before the process can move to the next phase; and
(2) Accept the certification report. If after
analysis the risk analyst accepts the Certification Report, which is included
in the certification package, the certification phase (phase II) is formally
completed and the accreditation phase (phase III) begins.
f. If a system does not meet certification
requirements for completion of phase II, the system will not be allowed to move
to phase III until certification and risk management verify and agree that phase
II requirements are met.
g. Items that may prevent completion of phase II
requirements are similar to the items listed in phase I.
5 FAH-11 Exhibit H-413.4-3
Phase III Accreditation
(CT:IAH-8; 12-22-2016)
a. When generating an Accreditation Report as part of
the authorization package, a risk analyst must:
(1) Characterize the acceptable amount of risk, based
on the information provided by the certification results;
(2) Provide an analysis of the current nature of
threats posed against a system; and
(3) Formalize a recommendation to DAA for approval or
denial of a system's authorization in an Authorization Memorandum, which is
included as part of the Accreditation Report.
b. The Accreditation Report must be reviewed and
cleared in IRM/IA in accordance with internal IRM/IA clearance processes. In
the review process, risk management must validate that the Accreditation
Report:
(1) Documents the assessed risk in the final risk
assessment;
(2) Validates the vulnerabilities identified in certification;
(3) Itemizes estimated costs for recovery and
replacement of systems with medium to high risk, (see the Departments IT Cost
Estimating Guide);
(4) Generates the systems initial POA&M report
listing the identified vulnerabilities in the Certification Report, finalized
in phase II; and
(5) Substantiates the recommendation to the DAA to
approve or deny authorization.
c. After receiving the Accreditation Report, which
must contain risk management's authorization recommendation, the DAA will
either accept or reject the report based on the residual risk posed to the
Department, and/or any documented business needs that may override security
concerns:
(1) If the DAA determines that issues in Accreditation
Report or accompanying Authorization Memorandum need resolving, then the
process cannot move forward until all issues are resolved to the DAAs
satisfaction; or
(2) If the DAA accepts and signs the Authorization
Memorandum in the Accreditation Report, it is forwarded from IRM/IA to the
sponsoring bureau for signatures.
d. Once the DAA signs the Authorization Memorandum, the
authorization decision is made final, and the process is allowed to move to phase
IV of the process:
(1) In cases where full authorization is granted and
all approving authorities have signed the Accreditation Report (i.e., DAA,
CISO, sponsoring bureau, and other designated key participants), the accreditation
phase (phase III) ends and the lifecycle monitoring phase (phase IV) begins.
(2) In cases of a denial of authorization to operate
due to medium or high risk, the CIO may direct operations to cease and the
system be disconnected and removed from the Departments integrated management,
analytics, and technology resource for information exchange as entered in
iMATRIX:
(a) Under special circumstances where a business need
overrides security concerns, the DAA may overrule a denial recommendation and
accept medium to high risk, in which case authorization may be granted. Prior
to this event, the sponsoring bureau must submit a memorandum to IRM/IA that
outlines a business case which demonstrates and justifies an overriding
business need for operations to continue, and which shows that all efforts to
reduce risk have been exhausted. Otherwise, at the discretion of the CIO,
operations will be discontinued; and
(b) Upon completion and validation of its remediation,
the system that received a denial to operate must be re-entered into and
successfully complete system authorization - from Phase I through end of phase
IV - to achieve DAA authorization to operate.
e. IRM/IA must ensure that original copies of the
completed authorization package sent to IRM/IA are scanned and converted to
".pdf" format (Adobe file format) for archival and inspection
purposes. Archived documentation (filed in both electronic and written form):
(1) Validates that system authorization is completed
in accordance with Department requirements (this subchapter);
(2) Supports OMB audit requirements; and
(3) Must be maintained throughout the life cycle of
the system, until disposal.
5 FAH-11 Exhibit H-413.4-4
Phase IV Life Cycle Monitoring
(CT:IAH-11; 08-10-2017)
a. Lifecycle monitoring activities performed by the
sponsoring bureau on behalf of systems should include, but are not limited to:
(1) System security management;
(2) Risk management review; and
(3) Configuration management and control of
information system components (see 5 FAH-5 H-521).
The sponsoring bureau must verify with the sponsored non-Department entity that
required configuration items exist, and current versions agree with the
specified requirements. Examples include:
(a) Documentation (specifically the SSP and CP);
(b) Source and executable code (changes to and
modification of function);
(c) Database and test database scripts and associated
access privileges;
(d) Modification to commercial-off-the-shelf (COTS)
and/or patches to COTS products and updates (see below GOTS); and
(e) Modification to U.S. Government-off-the-shelf (GOTS)
and/or patches to GOTS products and updates;
(4) Security impact analysis of changes to the
system. This includes integration testing and evaluation of new or modified
hardware or software for the enterprise network, as well as, coordination and
distribution of new releases of software updates and fixes (patches) and
version control;
(5) Ongoing assessment of security controls, including
but not limited to:
(a) Audit logs;
(b) User accounts and password settings; and
(c) System access permissions;
(6) System security requirements and status reporting;
and
(7) In meeting reporting requirements of annual
self-assessments, the sponsoring bureau must:
(a) Ensure that the required annual self-assessment is
conducted on the systems completing authorization, and ensure that the results
are recorded in the systems SSPs; and
(b) Report the self-assessment results to IRM/IA no
later than 30 days after completion of the self-assessment.
b. A Non-Department entity must initiate a new
authorization cycle if either (1) major modifications to the site IT
Infrastructure or (2) significant changes in threats or operating environment
occur. Otherwise, the system undergoes re-accreditation for the term defined
in the authorization.
c. Sponsoring bureaus must use the Department-approved
automated tools posted on the IRM/IA Web site to facilitate reporting the
self-assessment results of a system to IRM/IA.
d. For further guidance on management requirements in
life-cycle management, see 1 FAM 276.1-3.