5 FAM 850
CONTINUITY OF OPERATIONS AND CONTINGENCY PLANNING for information systems
(CT:IM-251; 11-21-2018) (Office of Origin: IRM/BMP)
5 FAM 851 REQUIREMENTS
(CT:IM-251; 11-21-2018)
a. In accordance with OMB A-130, every information system in the Department must have a contingency plan. This plan must be developed, documented, and tested each year for each general support system and major application.
b. System Administrators may download an appropriate contingency planning tool from the IRM/IA web page. For additional information on contingency planning see 12 FAH-10 H-232 and 12 FAM 632.3, along with NIST SP 800-34 Revision 1.
5 FAM 852 BACKUPS
a. Regardless of the size of the system, system and data files must be backed up regularly (at least once per week). The IMO/ISO/System Administrator has responsibility to:
(1) Establish a method and time for backups and adhere to the schedules;
(2) Determine which files are to be backed up, and when and how they will do it;
(3) Decide when to back up based on the local operational environment; and
(4) Notify users of backup schedules.
b. Copies of backup tapes or disks must be stored in a safe place off-site.
c. Users should back up critical files on their own PCs on an established schedule as a precaution.
d. See 12 FAH-10 H-232 for more information.
5 FAM 853 THROUGH 859 UNASSIGNED